JHU Building Critical Path Network Using the Given Template and Background PPT

JHU Building Critical Path Network Using the Given Template and Background PPT

I’m working on a management exercise and need support to help me study.

Calculate the Critical path network and draw on the PowerPoint images Use the provided CPM Network** to complete the following

1 Critical path

2. Node numbers

3 Durations

4 Earliest / Latest start and finish for each activity

5 Float for each activity

6 Major milestones***

7 Total time to complete this delivery order

***Note[3]: A milestone is a significant point in the project. Highlighted at the event (node), a milestone is often identified after the completion of a major event (review, submission of a significant deliverable, completion of a major test/demonstration, …). It is a point where the Project Manager assesses the current state of the project before progressing forward.

Background reference (for time durations of CPN)

1. Perform independent research on each of the five candidate IR sensors (2 weeks each for the Red-Eye series, one week each for the others).

2. Perform a trade study to down select to two IR sensor candidates (1.5 weeks).

3. Develop performance models for both IR sensor candidate sensors (6 weeks each). Note: These should be done separately but can be accomplished in parallel.

4. Develop a CONOPS to determine how IR / optical sensors are to be used on the X-65B (8 weeks).

5. Use the CONOPS and IR sensor performance models to develop / run independent performance simulations (4 weeks each). Note: These should be done separately but can be accomplished in parallel.

6. Use the outcome of your simulations as an input for a technical review to down select to a single IR sensor (preparations – 2 weeks).

7. Hold the IR sensor review and down select to a single IR sensor (1 day)

8. Perform research on the Eagle-Eye 2000® optical sensor (4 weeks).

9. Develop a performance model for the Eagle-Eye 2000® (2 weeks).

10. Update the performance model for the Tiger-Eye 1000® optical sensor (1 day).

11. Use the CONOPS and performance models to develop / run independent performance simulations (Tiger-Eye 1000® – 2 weeks, Eagle-Eye 2000® – 5 weeks)

12. Use the outcome of your simulations as an input for a technical review to down select to a single optical sensor (preparations – 2 weeks).

13. Hold the optical sensor review and down select to a single optical sensor (1 day). Please note that the IR sensor review and optical sensor review must be held separately but can occur in parallel. Page 2 Module 4 Assignment Building a Critical Path Network Management of Systems Projects Version 005_00b Revision

14. Design a common prototype hardware integration package to allow the selected IR / optical sensor to be mounted in the X65B. This mounting package must be designed in such a way to mount either the selected IR or optical sensor (dual use) (10 weeks). Note: This includes the development of a prototype to be used for hardware integration package testing (item15).

15. Test the hardware integration package and make required modifications (2 weeks).

16. Build three hardware integration packages (2 weeks total)

. 17. Design software to integrate the selected IR sensor with the X-65B mission computer (12 weeks).

18. Code IR sensor integration software (4 weeks).

19. Perform IR sensor software integration testing with the IR sensor and the X-65B simulator (3 weeks).

20. Design software to integrate the selected optical sensor with the X-65B mission computer (13 weeks).

21. Code optical sensor integration software (2 weeks).

22. Perform optical sensor software integration testing with the optical sensor and the X-65B simulator (3 weeks).

23. Install IR and optical sensors on the X-65B (2 days each – this can be done simultaneously, if required)

. 24. Perform final IR payload integration testing with the X-65B aircraft and make required changes (2 weeks).

25. Perform final optical payload integration testing with the X-65B aircraft and make required changes (2 weeks).

26. Develop test plan for X-65B live sensor testing (sensor independent – not dependent on selected sensors) (12 weeks).

27. Using the test plan, perform required hazard / safety analysis (3 weeks).

28. After completing the hazard / safety analysis, attain live sensor testing approval (6 weeks).

29. Perform X-65B live sensor tests (both sensors simultaneously) (2 weeks).

30. Develop live demonstration* plan, based on the outcome of the X-65B live sensor tests (1 week).

31. Make final changes to sensor payload configurations, based on live sensor tests (2 weeks).

32. Hold live demonstration* review (everything must be ready before this review occurs) (2 days).

33. Perform a practice series of dry run demos in preparation for the formal demonstration* (1 week).

34. *Perform live sensor demonstration (1 day).

35. Perform “hot wash” meeting after demonstration (1 day).

36. Write final close-out report, based on “hot wash” meeting (1 week).


Order Solution Now

Our Service Charter

1. Professional & Expert Writers: Studymonk only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided by Studymonk are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Studymonk is known for timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Studymonk, we have put in place a team of experts who answer all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.